Delayed
delivery of residential projects has become a significant issue on the
real estate market, leading to high levels of ire among
customers, says, Santhosh Kumar, CEO - Operations, Jones Lang LaSalle India.
In terms of the average delay in delivering residential
projects across India, more than 25% of the committed supply has not
been able to hit the market as per schedule. The National Capital
Region’s performance in terms of delivery of residential
supply due in 2013 has been the worst across all the major Indian
cities.
In
Gurgaon, only one-third of the total committed supply for 2013 has been
delivered so far. The situation has been even more alarming
in other NCR regions such as Noida, where only about one-fifth of the
residential supply committed for delivery in 2013 has been delivered so
far.
In
the West, Pune and Mumbai have shown a much better performance in terms
of project completions - these cities could deliver more
than 40% of the committed supply of 2013 as per scheduled delivery.
With
delivery delays, inventory levels across India have risen
significantly. The Pan India inventory of residential stock is now well
above the comfort level of 14-15 months. Mumbai has an inventory of
close to 48 months, Delhi of 23 months and Bangalore of 25 months. These
are close to the levels of 2007, when the residential real estate
market's inventories were at an all-time high.
Why Project Delays Occur
The
issues leading to residential project delivery delays are manifold.
Poor project management is often one of them, but this is not
essentially the prime reason. In fact, it is the current economic
scenario - defined by high levels of inflation and escalating
construction costs - that is the leading reason for delayed projects.
Developers are facing a severe liquidity crisis and do not
have the capital to complete their projects. However, there are also
other factors at play.
One
of these often is nothing more than a lack of commitment to timely
completion and delivery on the part of a developer. We are currently
looking at an environment wherein developers are obsessed with
launching new projects rather than making the completion of existing
projects a priority. There have been many instances where funds that
were raised for a particular project were diverted for
uses other than expediting the completion of projects under
construction.
Delay
in regulatory clearances is another critical reason for delays in
project deliveries. In many cases of delayed projects in Delhi
NCR, the water and sand crises as well as environmental regulations
which developers have not been able to meet have played a role. In quite
a few projects, the lag caused by various bureaucratic processes has
also been an operative factor in delayed project
clearances.
There
is no doubt that the new regulations pertaining to land acquisition
have thrown a rather massive spanner in the works. In the
NCR region, a significant number of residential projects in areas such
as Noida have been delayed because of disputes with regards to land
acquisition.
Advice For Property Buyers
In
the current scenario, the secondary market seems to be a more promising
avenue for end-user buyers, as they can get better price
points there. However, transactions on the secondary market often
require buyers to have higher initial liquidity so as to be able to meet
the immediate capital requirements. Also, in many of the projects,
developers have put in prohibitive measures such as
high transfer charges before the completion of the project. In such
cases, the valuation might also not be very attractive at all.
Nevertheless,
developers are feeling lot of financial pain and are now offering
attractive construction-linked and payment plans, with
the bulk of the payment phased towards the time of possession. These
plans allow buyers with limited liquidity to proceed with the purchase.
Also, CLPs mean that buyers have reduced exposure to the risk of delays.
We
expect that in the ensuing two quarters, developers will come out with
more incentives and discounts to attract buyers. In other
words, the primary market will continue to maintain its appeal. Buyers
are, as always, advised to do a complete and thorough due diligence of
the credibility of any developer they seek to deal with. Especially in
the current scenario, the delivery track record
for previous projects is a vitally important guideline for investment
in the primary market.
I think NCR is perfect place for investment, where you can get good return on your investment.
ReplyDeletePraneeth Pranav Valley